Keystone provided multi-disciplined engineering and design services to install all piping, pig traps, meters, and infield pipelines associated with a greenfield 200 MMSCFD gas plant. The project scope of work included piping, foundations, controls, and power interconnect associated with pig receivers and ultrasonic meter skids on incoming 12” and 24” gas lines. Additionally, the scope included a Coriolis meter skid on 16” export NGL line, 16” and 20” residue gas export lines, and pig receiver at remote surface interconnect site.
The pipeline scope included crossing and code calculations, material selection, hydraulics, and interface with the surveyor to develop alignment sheets associated with 12” and 24” incoming gas lines, and 16” and 20” residue gas export pipelines between the new Cryo plant and nearby surface
sites.