Shin Oaks Laterals

Midstream

Location

Nameplate Capacity

Keystone provided project management, engineering, design, and procurement support services for the detailed engineering design of three laterals as part of the larger pipeline system connecting Orla to Mont Beliveau. The client installed approximately 132 miles of 24” ANSI 600# pipeline to transport Y-Grade or Raw NGL mix from Orla, Texas to High Plains, Texas. Additionally, a 30-mile lateral receiving Y-Grade NGL from ARM and transporting to the Shin Oak pipeline. The scope of work included a Coriolis Meter, pig traps, and multiple MLV’s.

To learn more about our Renewable Energy department,
please click to visit our Renewables site.